Incident details

Major Outage Resolved

Chicago Datacenter Migration

Started Mar 23, 2026 at 17:00 UTC Resolved Mar 24, 2026 at 18:52 UTC
Our team will be landing in Chicago today to begin deracking all hardware and networking equipment for a migration to a new Ohio datacenter.
Status updates
Mar 23, 2026 at 11:30 UTC
Our team has arrived at YUL, departure for ORD scheduled for 8:30AM CDT.
Mar 23, 2026 at 18:58 UTC
Our team has arrived at the datacenter, deracking will start soon. Approximately 30 minutes.
Mar 23, 2026 at 22:37 UTC
Everything has been deracked in Chicago and is in route to the new Ohio facility.
Mar 24, 2026 at 03:33 UTC
Our team has arrived at the new location in Ohio and will start racking momentarily.
Mar 24, 2026 at 18:52 UTCLatest
Migration completed. All servers should be back online. If you are having trouble with your server, please contact us.